№p/b |
Event Title |
The cost of work (thous. UAH) |
Deadline (quarter) |
Responsible for implementation |
1 |
Repair of the roof and ventilation in academic building № 4 |
400 |
2-4 |
V. V. Shaparenko |
2 |
Placing the exhaust ventilation of premises where are kept reagent in the academic building № 4 |
50 |
2 |
V. V. ShaparenkoV. O. Vasylchenko |
3 |
Replacement of windows in academic building № 4 |
100 |
2-3 |
V. V. Shaparenko |
4 |
Strengthening of the foundations of educational building № 12 |
350 |
2-4 |
V. V. Shaparenko |
5 |
Repair of the STB roof in academic buildings № 9, 2, 14, 15 |
300 |
2-3 |
V. V. Shaparenko |
6 |
Repair of the blind area STB |
150 |
2-3 |
V. V. Shaparenko |
7 |
Shifting the heating system in educational building № 22 |
250 |
2-3 |
I. V. Levchuk |
8 |
Flushing the heating system in educational building № 13 |
25 |
2-3 |
I. V. Levchuk |
9 |
Reconstruction of sewage system in educational building № 13 |
40 |
2-3 |
I. V. Levchuk |
10 |
Repair of the electropane in educational building № 13 |
75 |
2-3 |
V. O. Vasylchenko |
11 |
Reconstruction of lighting in KPI park |
75 |
2-3 |
V. O. Vasylchenko |
12 |
Remaking the cable network 10 kV from TP-3644 – TP-3643 |
500 |
2-3 |
V. O. Vasylchenko |
|
In all |
2 315 |
|
|